So, what exactly do you need for a G99 application?
In this guide, we’ll walk through the key documents, explain why each one matters, and share practical insights to help UK solar installers prepare their applications more effectively.
What Is a G99 Application?
G99 refers to Engineering Recommendation G99, published by the Energy Networks Association (ENA). It sets out the requirements for connecting generating equipment, such as solar PV systems and battery storage, to Great Britain’s electricity distribution networks.
In simple terms, it helps ensure that a generation system can operate safely and reliably alongside the existing electricity network.
A G99 application is generally required for generation installations that fall outside the scope of G98. This commonly includes installations exceeding 16A per phase, although the applicable connection route depends on the system and relevant technical requirements.
For installers, the application involves more than providing the system size. The DNO needs sufficient technical information to assess the proposed connection, understand how the equipment will operate and determine whether any network upgrades or additional conditions are necessary.
Important: G98 and G99 are not interchangeable application options. Always check the applicable ENA requirements and the relevant DNO’s process before deciding which route applies.
What Documents Do You Need for a G99 Application?
The exact documentation depends on the project, generating capacity, equipment and connection arrangement. However, the following documents and technical information are commonly required when preparing a G99 application.
1. Completed G99 Application Form
The application form is the starting point of the process. It provides the DNO with an overview of the proposed generation system and its connection to the electricity network.
Installers should be prepared to provide:
- Site address and installation details.
- Customer and applicant information.
- Proposed generation capacity.
- Number and type of inverters.
- Existing and proposed generation at the property.
- Proposed connection date.
- Details of the existing electricity supply.
Make sure the information is consistent across the application form and supporting documents. Even a small difference in inverter capacity or equipment details can result in clarification requests.
2. Single Line Diagram (SLD)
A Single Line Diagram is one of the most important technical documents in a G99 application.
It provides a simplified electrical representation of the installation, showing how the solar PV system connects to the property’s electrical infrastructure and the wider distribution network.
A typical DNO-format SLD may include:
- Solar PV modules and inverter arrangement.
- AC and DC isolation points, where applicable.
- Main distribution board and connection point.
- Metering arrangements.
- Protective devices and circuit breakers.
- Earthing arrangements.
- Battery storage equipment, if included.
- Export limitation equipment, where applicable.
The SLD should accurately reflect the proposed installation. If the equipment listed in the application form does not match the diagram, the DNO may request further information.
This is why accurate solar SLD design is an important part of preparing a G99 application.
3. Inverter Technical Datasheets
The DNO needs to understand the electrical characteristics of the inverter being installed.
Provide the manufacturer’s technical datasheet for each proposed inverter model. Depending on the application, the information may include:
- Manufacturer and model number.
- Rated AC output power.
- Maximum apparent power (kVA).
- Rated voltage and frequency.
- Number of phases.
- Power factor capability.
- Maximum output current.
- Relevant protection and operating characteristics.
For systems using multiple inverters, include details for all units.
Installer tip: Always check the exact inverter model and variant. Similar-looking products from the same manufacturer may have different technical specifications.
4. ENA Type Test Evidence
The DNO may require evidence that the generating equipment meets the relevant technical requirements.
For inverter-based systems, this commonly involves an appropriate ENA Type Test Register entry or supporting type-test documentation.
This evidence helps demonstrate that the inverter has been assessed against the relevant grid connection requirements.
Before submission, check:
- Whether the exact inverter model appears on the relevant ENA register.
- Whether the listed firmware or software version is applicable.
- Whether the certification covers the intended operating configuration.
- Whether the evidence is appropriate for the applicable G99 requirements.
Using an inverter with suitable type-test evidence can simplify the technical assessment. However, installers should not assume that every model from a particular manufacturer has the same approval status.
5. Protection Settings and Relay Information
Protection is an essential part of any grid-connected generation system.
The DNO needs to understand how the installation will respond to abnormal network conditions, including voltage and frequency disturbances.
Depending on the system design and connection arrangement, the application may require:
- Protection relay details.
- Overvoltage and undervoltage settings.
- Overfrequency and underfrequency settings.
- Loss-of-mains protection information.
- Interface protection details.
- Protection equipment specifications.
- Relevant test or commissioning information.
The exact requirements depend on the applicable G99 connection type and whether protection is provided through the inverter or a separate interface protection arrangement.
Installers should avoid using generic protection settings without checking the manufacturer’s documentation and the relevant DNO requirements.
6. Site Layout and Location Plan
A site layout or location plan helps the DNO understand where the proposed generation equipment will be installed.
It can be particularly useful for larger commercial systems or installations with more complex electrical arrangements.
Depending on the project, the drawing may show:
- Property and site boundaries.
- Existing electricity supply location.
- Proposed point of connection.
- Inverter and generation equipment locations.
- Transformer or switchgear locations, where applicable.
- Relevant cable routes and electrical infrastructure.
For larger installations, the DNO may request more detailed site drawings to support its assessment.
7. Export Limitation Scheme Details (Where Applicable)
Some solar installations are designed to limit the amount of electricity exported to the distribution network.
Where an export limitation scheme is proposed, the DNO may require technical details demonstrating how the export limit will be achieved and maintained.
Supporting information may include:
- Export limitation device specifications.
- Control and monitoring arrangements.
- Current Transformer (CT) details.
- Connection and control wiring diagrams.
- Maximum export capacity.
- Relevant G100 compliance evidence.
G100 is particularly relevant where a customer wishes to connect generation with an export limitation scheme.
It is important to remember that an export limitation arrangement does not automatically remove the need for a G99 application. The applicable connection requirements must still be assessed.
8. Battery Storage Technical Information (If Applicable)
If the project includes battery energy storage alongside solar PV, the DNO needs to understand how the combined system will operate.
Battery systems can introduce additional charging, discharging and export considerations.
Depending on the design, supporting information may include:
- Battery manufacturer and model.
- Battery capacity (kWh).
- Maximum charge and discharge power.
- Battery inverter specifications.
- Operating modes.
- AC or DC coupling arrangement.
- Export limitation strategy.
- Relevant protection and control information.
For solar-plus-storage projects, ensure that the application reflects the complete generation and storage arrangement rather than treating the solar inverter as the only relevant equipment.
Why Do G99 Applications Get Delayed?
Even when installers understand the G99 process, documentation issues can create unnecessary delays.
Here are some common problems to watch out for:
1. Incomplete application information
Missing equipment details, generation capacity or connection information can prevent the DNO from completing its assessment.
2. Incorrect or inconsistent SLDs
If the Single Line Diagram does not match the equipment specifications or application form, the DNO may request clarification.
3. Incorrect inverter documentation
Submitting a datasheet or type-test certificate for a different inverter model or configuration can create additional technical questions.
4. Missing protection information
Protection settings and interface arrangements need to be appropriate for the proposed system and applicable connection requirements.
5. Changes to the system after submission
Changing the inverter, generation capacity or export arrangement after submitting an application may require revised documentation and further DNO review.
The best way to reduce these issues is to review the entire application package before submission, rather than checking each document in isolation.
How a Solar Engineering Partner Can Help with G99 Applications
Preparing a G99 application involves several technical documents that need to work together. For solar installers managing multiple projects, handling all this engineering documentation internally can become time-consuming.
This is where an experienced solar engineering partner can add value.
A specialist engineering team can support installers with:
- G99 application documentation: Preparing and reviewing the technical information needed for submission.
- Single Line Diagram design: Developing accurate electrical diagrams that reflect the proposed installation.
- Inverter and equipment verification: Checking manufacturer specifications and relevant technical evidence.
- Protection documentation: Supporting the preparation of protection-related information in line with project requirements.
- G100 export limitation support: Preparing relevant technical documentation for applicable export limitation schemes.
- Technical query support: Helping address DNO requests for additional information and revised documents.
At Vishtik Technologies, we support UK solar installers with DNO application assistance and Solar Single Line Diagram (SLD) design.
Our aim is to make the engineering and documentation side of solar projects easier to manage, allowing installers to focus on installations, customers and business growth.
Welll…..
A well-prepared G99 application starts with accurate engineering and the right documentation.
From application forms and inverter specifications to protection details and Single Line Diagrams, every technical detail matters when submitting a grid connection application to the DNO.
For UK solar installers, getting these details right can help minimise avoidable queries, reduce documentation rework and keep projects progressing smoothly.
At Vishtik Technologies, we work as an engineering partner to help solar installers simplify the technical side of grid connections with reliable DNO application assistance and expert professional SLD design.
Let’s make your next solar grid connection project easier to manage.